①預(yù)處理水封井排水標準,液位到達池口20-50cm時進行排水,排潛水泵露出頂部停止排水,排水不定期。
① The drainage standard of the pre-treatment water sealed well is that when the liquid level reaches 20-50cm at the pool mouth, the water shall be drained until the top of the submersible pump is exposed, and the drainage shall be stopped irregularly.
②廢水井排水,在液下泵無自動情況下,液位到達池口20-50cm時進行排水,排潛水泵露出頂部停止排水,排水不定期;目前液下泵自動運行,關(guān)液下泵運行狀況即可。
② The waste water well shall be drained when the liquid level reaches 20-50cm at the pool mouth when the submerged pump is not automatic, and the drainage shall be stopped when the submersible pump is exposed to the top, and the drainage shall be irregular; At present, the submerged pump operates automatically, and the operation status of the submerged pump can be turned off.
③洗滌塔運行中液位到達400m進行補水,補800m后,停止補水,開關(guān)水閱即可洗滌塔補水期間嚴禁人員離開,補水結(jié)束后方可離開,以免發(fā)生洗滌塔高液位,水倒罐沼氣管道,造成水培。 ④氣柜水封井在液位到達潛水泵四分之三處,進行排水,閉合AA1配電柜中QF119,啟動水泵,液位到達潛水泵露出三分之二,拉下QF119,停止排水。
③ Make up water when the liquid level of the scrubber reaches 400m during operation. After making up to 800m, stop making up water and turn on and off the water. Personnel are strictly prohibited to leave during the water making up of the scrubber. Only after the water making up is completed can they leave, so as to avoid high liquid level of the scrubber and water pouring into the biogas pipeline, resulting in hydroponic culture. ④ When the liquid level of the water seal well of the gas holder reaches three-quarters of the submersible pump, drain water, close qf119 in Aa1 distribution cabinet, start the water pump, when the liquid level reaches two-thirds of the submersible pump, pull down qf119 and stop drainage.
⑤再生池補排水、補水:開啟再生池補水手閥,再開啟軟化水總即可,待液位補目標液位時,必須先關(guān)閉軟化水總閥,再關(guān)閉再生池補水閥,排水:開啟老沉淀池進料閥,開啟循環(huán)泵到老沉淀池手閥,開度50%以下開度超過50%會影響噴淋流量,造成塔內(nèi)吸收效果變差,出口硫化氫超標,排目標液位依次關(guān)閉相應(yīng)手閥即。
⑤ Make up drainage and water supply of the regeneration tank: open the make-up valve of the regeneration tank, and then open the demineralized water main valve. When the liquid level is made up to the target liquid level, you must first close the demineralized water main valve, and then close the make-up valve of the regeneration tank. Drainage: open the feed valve of the old sedimentation tank, and open the hand valve from the circulating pump to the old sedimentation tank. The opening is less than 50%, and more than 50% will affect the spray flow, As a result, the absorption effect in the tower becomes worse, and the outlet hydrogen sulfide exceeds the standard. When it is discharged to the target liquid level, close the corresponding hand valves in turn.
注:水封井液位每日巡檢一次即可,雨雪天氣,增大巡檢頻率,以免水封井液位過高,造成氣路水堵,導(dǎo)致氣柜喪失緩沖能力。
Note: the liquid level of the water seal well can be inspected once a day. In rainy and snowy weather, increase the inspection frequency to avoid the high liquid level of the water seal well, resulting in water blockage in the gas path and loss of buffer capacity of the gas holder.